Please see the anticipated general schedule below:
May 14 Bid opening for paving of W Creek Rd – (Lian Dr to Rt 52)
May 29 & 30 paving of wall section of W Creek Rd (this will complete the Wall project)
June & July public works to do some base repair and drainage work in-house along with chip seal of roadway.
Mid to late August ’24 complete overlay of W Creek –( Lian Dr to Rt 52)
Please follow the route highlighted in the map below as the detour during scheduled construction hours. (Lenape, S Creek, Bridge, 842, and S Wawaset Roads.) Please enter gravel road at open gate.